Hi,
Currently, I have created several projects in the same workspace.But I found that the PSoC Creator default setting is that always build the or latest new project,so I can't build and program the previous projects. My question is that how can I customize the project build order?
PS: I found the "build order" by right click the project name, but it doesn't work.
Thanks.
Ocean
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Hi HaHu_4715551,
Can you please let me know if there is any particular reason you would want the build order to change?
But I found that the PSoC Creator default setting is that always build the or latest new project,so I can't build and program the previous projects.
When you click on Build, PSoC Creator builds the currently active project. To change the active project, you can right-click on the project in the Workspace Explorer and then click on Set As Active Project.
PS: I found the "build order" by right click the project name, but it doesn't work.
Yes, the Build Order tab is a read-only list of the order in which your projects will build if you select Build all projects.
This is one way in which you can change the Build Order -
Let's say you have 4 projects, P3, P4, P5, P6 in your Workspace and the current Build Order is P6, P5, P4, P3. Now if you need to change the build order to P5, P6, P4, P3, you can modify the P6 project and provide P5 as one of the dependency.
Right-click on the project/workspace and select Dependencies. Select the appropriate project and you can modify the project's dependencies. Here I have added P5 as the dependency for P6 and the build order changed i.e., P5 is built before P6.
Please let me know if this helps.
Thanks and Regards,
Rakshith M B
Rakshith M B
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Hi HaHu_4715551,
Can you please let me know if there is any particular reason you would want the build order to change?
But I found that the PSoC Creator default setting is that always build the or latest new project,so I can't build and program the previous projects.
When you click on Build, PSoC Creator builds the currently active project. To change the active project, you can right-click on the project in the Workspace Explorer and then click on Set As Active Project.
PS: I found the "build order" by right click the project name, but it doesn't work.
Yes, the Build Order tab is a read-only list of the order in which your projects will build if you select Build all projects.
This is one way in which you can change the Build Order -
Let's say you have 4 projects, P3, P4, P5, P6 in your Workspace and the current Build Order is P6, P5, P4, P3. Now if you need to change the build order to P5, P6, P4, P3, you can modify the P6 project and provide P5 as one of the dependency.
Right-click on the project/workspace and select Dependencies. Select the appropriate project and you can modify the project's dependencies. Here I have added P5 as the dependency for P6 and the build order changed i.e., P5 is built before P6.
Please let me know if this helps.
Thanks and Regards,
Rakshith M B
Rakshith M B
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Hi Rakshith,
Thanks for your help from bottom of my heart.Your answer is exactly what I need.
Best Regards,
Ocean
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Hi Ocean,
Glad it helped
Thank you for providing an update on the thread.
Best Regards,
Rakshith
Rakshith M B